The three contract questions I'd ask before you sign, how I'd handle every open item at the end of a build, the questions before the last payment, and the punch list email I'd send, word for word.

01 Hold a list, not just the money

On November 9, 2026, an Indiana appeals court ruled that a couple owe their builder $221,704, more than their whole house cost. They'd held back about half of the price until things got fixed.

You've probably heard the advice online: never make the final payment until everything's done. That's pretty much what they did. But there was no signed list of what fixed meant. Money you hold back only works when it's tied to a list you both wrote down.

That list really starts long before the end, the day you sign. Most builds pay in steps. The foundation's done, you pay a draw, which is just one planned payment. The house is framed, you pay the next one. And the last one comes at the end. The page in the contract that lists when each payment is due is called a payment schedule. This contract had none, so when they disagreed at the end, there was no list in between.

02 Three questions before you sign

Before you sign with a builder, I'd take these three questions to the table.

What is each payment tied to? And especially the last one? Is the last one tied to the punch list being finished, to a final walkthrough, or to the house passing its final inspection? Get the answer in writing, in the contract.
Who pays the lawyers if this ever ends up in court, and does that go both ways? The contract in the Indiana case let the builder get its legal fees back if it won. It also put a ceiling on what the homeowners could ever claim: at most, the cost of the repairs or what the house lost in value, and only the smaller of the two. Read those lines before you sign them, not after.
What's on my side of the list? Splitting the work is really common. In that contract, the builder had the foundation and the plumbing, and the homeowners had things like the gutters, the power hookup and the well. Know your own items before the end, because if yours aren't done, the builder can't finish its own.
My contract check
Each payment is tied to: ___
The last payment is tied to: punch list finished / final walkthrough / final inspection
Who pays the lawyers: ___ Both ways: yes / no
Limit on what I can claim: ___
My items on the list: ___
03 Every open item, three ways

A punch list is the list of last fixes before a house is done, and who's doing each one. I teach that every open item on it is three things: documented, acknowledged, and scheduled. Written down, agreed by the builder, and given a date.

Documented: every worry goes on the list before you sign off on anything. Yours, and your inspector's, each one with a photo. If it's not on the list, nobody's agreed to fix it.
Acknowledged: the builder answers each item in writing. Not "Okay, that's fine," but a reply that names it, or their initials next to it.
Scheduled: every item gets a name and a date. Who's fixing it, and by when.

In the Indiana case, the list both sides were working from said nothing about moisture in the crawl space, the low space under the house. That was the very thing that worried the homeowners a few weeks later.

If something big comes up, don't panic. Problems at the end of a build are normal. Ask what happened, why it happened, and what the best fix is. None of those is about blame. Then let them in to finish, and confirm every visit in an email.

04 Before the last payment

Before the final payment, ask the builder three things.

What's still open? Every item not checked off yet.
When will it be done? A date for each one.
And who's responsible? A name for each one, the builder's or yours.

This is the email I'd send with the list, word for word. Fill in the blanks and attach your photos.

The punch list email
Subject: Our punch list for the house

Hi ___,

Here is our punch list for the house. It has every worry we have, ours and our inspector's, each one with a photo.

Could you answer each item in writing? A reply that names the item, or your initials next to it, is perfect.

Then could you give every item a name and a date: who's fixing it, and by when?

Before the final payment, could you also tell us:
1. What's still open?
2. When will it be done?
3. Who's responsible?

Our own items on the list are: ___. We'll let you know as each one is done, so you can finish yours.

When your crew comes out, I'll confirm each visit in an email.

Thank you,
___

When that last item is checked off, you've got a real reason to make the last payment. And that's when you get your keys.

Hold a list, not just the money.

Sources

Nicole's LibraryLibrary card
Free access

Keep reading free with your library card

One email opens this checklist and all 21 resources in Nicole's library. No account, no password.

It opens right here, and a copy goes to your inbox. You'll also get Nicole's new resources. Unsubscribe in one click.

Thanks
You finished it
Now do one thing

Open your contract, find the line about the last payment, and check what it's tied to: the punch list being finished, a final walkthrough, or the house passing its final inspection.