The Finish Order Checklist

Every finish choice in the order I'd make it, a place for the date each one is due, and three ways to keep the finishes from waiting on you.

01 Why the finishes take longest

On November 2, the National Association of Home Builders, America's home builders' group, shared what builders told them in their October survey about how long each stage of a new house takes. The whole house came out to about 25 weeks. Framing takes a little under four weeks. The interior finishes take 6.4 weeks, longer than any other stage, and they're about a quarter of what it costs the builder to build the house.

What counts as a finish: the drywall, the interior doors, the paint, the cabinets, the countertops, the floors, even the sinks and the faucets. Everything you actually touch and look at every day. Why it's slow: finishes are a line of trades. The floors go in, then the cabinets. Then there's a pause before anyone can measure for the countertops, because they measure the real cabinets, not the drawing. Then the backsplash goes up, and the faucet goes on last. Who the survey is about: homes builders build to sell. If you're building a custom home on your own lot, it's longer. The same builders' group puts a custom home at about fourteen months, from the permit to done.

In your build, the line has one more thing it can wait on, and that's you. Which floor, which cabinets, which tile. The crew can't keep going until you decide.

During the pause. It can look like nothing is happening. Just because you don't see progress doesn't mean progress isn't happening.

02 Pick in this order

Most people start with the paint, and then the floor and cabinets they want don't go with it, or aren't ordered yet. That's how a crew ends up in your kitchen with nothing to install. Here's the order I'd make your choices in, on paper, before the first shovel goes in the ground.

1. Flooring. It comes first. The cabinets and everything after it are chosen to look right next to it.
2. Cabinetry. Once your floor is picked, the thousand cabinet colors you've saved become maybe ten.
3. Countertops. Each choice gets made around the one before it, so the counters are picked to go with your cabinets.
4. Tile. The backsplash goes up once the counters are in.
5. Plumbing fixtures and hardware. The sinks, the faucets, the handles and pulls.
6. Paint, near the very end. It's one of the easiest things to change, so it's one of the last things I decide.
Big decisions first, little decisions second.
03 Put a date on every choice

Your builder will give you a deadline for your selections. Selections is just the builder's word for every finish you choose. But that deadline is the day they need it, not the day you should start. So ask them one question, finish by finish:

Ask your builder. When do you need my decision on each finish?

Then put your own date on every decision. Instead of saying "I'll think about it", say "I'll make this decision by Friday." Fill in the sheet below with your builder, and keep it where you'll see it.

My finish dates
Finish | Goes in around (ask your builder) | Builder needs my decision by | I'll decide by | Ordered on
Flooring | ___ | ___ | ___ | ___
Cabinetry | ___ | ___ | ___ | ___
Countertops | ___ | ___ | ___ | ___
Tile | ___ | ___ | ___ | ___
Plumbing fixtures | ___ | ___ | ___ | ___
Hardware | ___ | ___ | ___ | ___
Paint | ___ | ___ | ___ | ___
04 Once it's ordered, stop shopping

Once you've ordered the tile, stop looking at tile, because changing one finish is never just one change. Swap the floor, and now the stairs, the baseboards and the cabinet color are all back on the table. One decision turns into seven.

Later has a funny way of arriving much faster than people think. It happens to me too: years ago, we thought we'd move into our own renovation after six months, and it took about a year and a half. One home builder told a company that sells software to builders that the biggest cause of delays on custom homes is the homeowner making their choices late, ahead of the weather, the permits and material shortages. That's one builder, but from what I've seen on job sites, it's not far off.

I asked when my builder needs each decision. Their deadline is the day they need it, not the day I start.
Every decision has my own date. "I'll make this decision by Friday", never "I'll think about it".
Whatever is ordered, I've stopped shopping for. One swap puts seven decisions back on the table.

You can't make paint dry any faster, but you can make sure nobody on your job site is standing around waiting on you.

The key isn't making all the decisions faster, it's knowing which decisions to make first.

Sources

Nicole's LibraryLibrary card
Free access

Keep reading free with your library card

One email opens this checklist and all 21 resources in Nicole's library. No account, no password.

It opens right here, and a copy goes to your inbox. You'll also get Nicole's new resources. Unsubscribe in one click.

Thanks
You finished it
Now do one thing

Ask your builder when they need your decision on each finish, then write your own date next to each one.