They Held Back $110,235 From Their Builder. The Court Ruled They Owe $221,704

A builder sold an Indiana couple a house for $211,235, and a court ruled they owe $221,704. How I'd handle the last payment and the punch list.

Nicole Roe
Luxury interior designer, founder of R. Nickson Interiors
November 16, 2026
Watch the video, or read the article below.
7:48

Callaghan Homes sold an Indiana couple a house for $211,235. And on November 9, a court ruled they owe that builder $221,704.

At the trial, the husband said they still didn’t have a key, and that they wouldn’t take the house as it stood.

If you’re about to build, I want you to hear how this happened, because it started with one line in a contract. I studied building construction, and on my projects I sit right between the homeowner and the builder. You’ve probably heard the advice online: never make the final payment until everything’s done. Well, that’s pretty much what they did. So here’s what the court’s decision says.

One line in the contract

In December 2021, they signed for a modular home, the kind that’s built in a factory and set on your lot by a crane. With one stove added, the price came to $211,235. And in the contract, there was one line about the end:

Keys and possession upon final full payment.

Meaning no keys until every last dollar is paid. Then in October 2022, the crane set the house on their lot, in two halves. That December, they paid $100,000 on top of a deposit of $1,000. So about half was paid, and they still owed $110,235.

The punch list, and the crew told to leave

Early in 2023, the builder sent them a punch list. That’s just the list of last fixes, and who’s doing each one. Then their own inspector came out in March and found things that worried them, like floors that sloped and water in the crawl space, the low space under the house. That same month, the project manager came by to keep working through the list. The court found they told him to leave, and the crew never got back on the property.

And honestly, I get it. You see water under your new house, and you don’t want anybody touching anything.

Something less than perfection

Does that mean you should just pay and stay quiet? No. The court took $8,800 off what they owed, for work that wasn’t finished. But it also said a builder who has done most of the job is owed most of the price. The court quoted an old rule from an earlier case: “Something less than perfection is the test.” In plain English, a builder doesn’t have to be perfect to get paid.

Then there’s the bill. They owe $101,435 on the house. On top of that, $105,419 for the builder’s lawyers. And $14,850 for expert witnesses. So with what they’d already paid, that house ends up costing them about $322,700, plus interest.

Chart from the video: the bill stacked above the house price, what was already paid, $101,435 on the house, $105,419 and $14,850, about $322,700 in all
2:35 in the video with what they’d already paid, that house ends up costing them about $322,700, plus interest

Hold a list, not just the money

This is one case in one state, and a decision like this doesn’t even count as a rule for other cases in Indiana, meaning other judges don’t have to follow it. But the lesson still applies anywhere you build.

They kept the unpaid half until things got fixed, but there was no signed list of what fixed meant. And money you hold back only works when it’s tied to a list you both wrote down. That’s why I teach that every open item at the end of a build is three things: documented, acknowledged, and scheduled. Written down, agreed by the builder, and given a date.

I put the questions I’d ask about the last payment, and the punch list email I’d send, into one free checklist.

So hold a list, not just the money. And that list really starts long before the end, the day you sign.

A contract with no payment schedule

Callaghan Homes’ contract for an Indiana house had no page that said when to pay, and the fight over the last payment went all the way to an appeals court. Most contracts have one. It’s called a payment schedule, and it lists when each payment is due.

Most builds pay in steps. The foundation’s done, you pay a draw, which is just one planned payment. The house is framed, you pay the next one. And the last one comes at the end. In this contract there were no steps. So when they disagreed at the end, the builder wanted the whole balance, the homeowners wanted the house fixed first, and there was no list in between.

Three questions before you sign

Before you sign with a builder, I’d take three questions to the table.

1. What is each payment tied to? And especially the last one. Is it tied to the punch list being finished? Or to a final walkthrough, or to the house passing its final inspection? Get the answer in writing, in the contract.

2. Who pays the lawyers if this ever ends up in court, and does that go both ways? This contract let the builder get its legal fees back if it won. So if it ended up in court and the builder won, the homeowners would pay the builder’s lawyers too. And it put a limit on what the homeowners could ever claim. So even if something went wrong, there was a ceiling on what they could get back: at most, the cost of the repairs or what the house lost in value, and only the smaller of the two. So read those lines before you sign them, not after.

3. What’s on my side of the list? This contract split the work, which is really common. The builder had the foundation and the plumbing. The homeowners had things like the gutters, the power hookup and the well. So know your own items before the end, because if yours aren’t done, the builder can’t finish its own.

I’m a designer, not a lawyer. Every state and every contract is different. So take these three questions to an attorney before you sign, and before you ever hold back a payment. All three are on my free checklist, worded the way I’d ask them.

The Final, Final Punch List

Then one day the house is almost done, and the list shows up.

Callaghan Homes’ project manager emailed an Indiana couple “the Final, Final Punch List.” They never signed it, and more than three years later, an appeals court sided with the builder.

He sent it in February 2023, and it said who would do each item: the builder, the homeowners, or the factory that built the house. He asked them to print it and sign it. The husband wrote back, “Okay, that’s fine.” The builder took that as a yes, but it was never signed.

When the builder sued them, the court noted something. That list said nothing about moisture in the crawl space, under the house, the very thing that worried them a few weeks later. So what they cared about most wasn’t on the list both sides were working from.

This part is easy to miss. When the project manager came back that March, the court found he was there for the gutters and the electric line. Those were on the homeowners’ side of the list. And the builder’s last bit of grading was waiting on them. That’s shaping the ground so water runs away from the house.

Documented, acknowledged, scheduled

Here’s how I’d handle the end, with every open item documented, acknowledged and scheduled.

  • Documented means every worry goes on the list before you sign off on anything. Yours, and your inspector’s, each one with a photo. If it’s not on the list, nobody’s agreed to fix it.
  • Acknowledged means the builder answers each item in writing. Not “Okay, that’s fine,” but a reply that names it, or their initials next to it.
  • Scheduled means every item gets a name and a date. Who’s fixing it, and by when.

Then before the final payment, you ask the builder three things. What’s still open? When will it be done? And who’s responsible?

Illustration from the video: a punch list with each item, who is fixing it and by when, and the finished items checked off
7:35 in the video every item gets a name and a date. Who’s fixing it, and by when

Don’t panic, and let them finish

If something big comes up, don’t panic. Problems at the end of a build are normal. Ask what happened, why it happened, and what the best fix is. Notice that none of those is about blame. Then let them in to finish, and confirm every visit in an email.

The email I’d send with that list is in my free checklist, word for word.

So when that last item is checked off, you’ve got a real reason to make the last payment. And that’s when you get your keys.

Does your contract say what your last payment is tied to?

Questions people ask

Should I hold back the final payment until everything’s done?

Money you hold back only works when it’s tied to a list you both wrote down. In this case, they kept the unpaid half until things got fixed, but there was no signed list of what fixed meant.

Does a builder have to be perfect to get paid?

The court quoted an old rule from an earlier case: “Something less than perfection is the test.” In plain English, a builder doesn’t have to be perfect to get paid.

What is a payment schedule in a construction contract?

It lists when each payment is due. Most builds pay in steps: the foundation’s done, you pay a draw, which is just one planned payment. The house is framed, you pay the next one. And the last one comes at the end.

What should I ask a builder before I sign?

What is each payment tied to? Who pays the lawyers if this ever ends up in court, and does that go both ways? And what’s on my side of the list?

How do I handle the punch list at the end of a build?

Every open item is documented, acknowledged and scheduled. Written down, agreed by the builder, and given a date.

What should I ask before the final payment?

What’s still open? When will it be done? And who’s responsible?

Sources

  1. Indiana Court of Appeals, memorandum decision 26A-⁠⁠PL-⁠⁠1342 (November 9, 2026)

Your next step

01

This checklist · free

The Last Payment Checklist

The three contract questions I’d ask before you sign, how I’d handle every open item at the end of a build, the questions before the last payment, and the punch list email I’d send, word for word.

Your first moveOpen your contract, find the line about the last payment, and check what it’s tied to: the punch list being finished, a final walkthrough, or the house passing its final inspection.

02

Nicole’s Library · free

Get free access to Nicole’s whole library

One email opens every checklist from Nicole’s videos, right here on the site, and each new one as she adds it.

  • Who Gets a Vote Checklist
  • Stay-⁠⁠⁠or-⁠⁠⁠Go Checklist
  • Teammate Ladder: How to Raise a Problem With Your Builder
  • Kitchen Traffic Checklist
  • Open Walls Checklist
  • Cushion: Your Renovation Budget Template
  • Electrical Walkthrough Checklist
  • Last Payment Checklist
  • Kids’ Room Furniture Checklist
  • Lineup: Your Trade-⁠⁠⁠by-⁠⁠⁠Trade Decision Checklist
  • New Build Protection Checklist
  • Laundry Walk-⁠⁠⁠Through Checklist
  • Decide Together Worksheet
  • Appliance Specs Checklist
  • Lighting Plan Checklist
  • Finish Order Checklist
  • Before-⁠⁠⁠Drywall Checklist
  • Contractor Interview Checklist
  • Cabinet Order Checklist
  • Countertop Promise Checklist
  • Picture-⁠⁠⁠to-⁠⁠⁠Plan Checklist

03

Work with Nicole

Already mid-⁠⁠project?

Through R. Nickson Interiors, my team designs and manages whole-⁠⁠home projects. Or learn the process yourself with The Highly Designed Home Method.

Free, by email

Follow by email: Nicole's new resources

New checklists and articles from Nicole's videos, as she adds them.

Free checklists, templates, and guides from Nicole's videos
For your build or renovation: the process, design decisions, and life mid-⁠⁠build
You confirm on Nicole's Library.
Your email stays with Nicole and the team that runs this library. Never sold.
Thanks
Share this article
Nicole Roe
Written by

Nicole Roe

Luxury interior designer, founder of R. Nickson Interiors

I studied building construction at Georgia Tech, and I run R. Nickson Interiors, a full-⁠⁠service luxury interior design firm that takes on 10 to 12 projects a year. Our work has been in Architectural Digest and HGTV Magazine, and on the cover of Kitchen & Bath Business. I speak at High Point Market. Every resource here is built from my videos and fact-⁠⁠checked.

Architectural Digest work featured HGTV Magazine work featured Kitchen & Bath Business on the cover High Point Market speaker Georgia Tech building construction
About Nicole
Keep watching

More from Nicole

All videos
Video thumbnail: Everyone Gets an Opinion. Not Everyone Gets a Vote: How to Handle Comments on the House You're Building
Nov 23

Everyone Gets an Opinion. Not Everyone Gets a Vote: How to Handle Comments on the House You’re Building

A colorful house got a comment joking about divorce papers. How to handle comments on the house you're building: one rule, and three steps.

Video thumbnail: Their Renovation Moved Them In With Mom. Should You Move Out?
Nov 22

Their Renovation Moved Them In With Mom. Should You Move Out?

One broken light switch is the reason Kaylei Fleming's family ended up living with her mom. Should you move out, or stay and live through it?

Video thumbnail: One TikTok About Singh Homes Cost a Homeowner A$883,000. How I'd Raise a Problem Instead
Nov 21

One TikTok About Singh Homes Cost a Homeowner A$883,000. How I’d Raise a Problem Instead

An Australian court ordered a homeowner to pay 883,000 Australian dollars over one TikTok about his builder. Here's how I'd raise a problem instead.