The Lineup: Your Trade-by-Trade Decision Checklist
Nicole RoeChecklist · 4 min read

The Lineup: Your Trade-by-Trade Decision Checklist

The trade schedule, every decision lined up under the trade that needs it, one place for all of it, and the order-by dates, on one checklist you can hand to your builder.

01 Two timelines

Home building lost 16,400 jobs in October, and almost all of them were the trades: your electrician, your plumber, the drywall crew, the tile setter, the painter. You can't make more trades show up. But you can be the job that's ready when they pull up.

There are two timelines on every build. The construction timeline is the trades. The decision timeline is you. The goal is to keep the decision timeline one step ahead of construction.

Here's what falling behind looks like. Your tile setter shows up, and nobody's picked the tile yet. He goes to set tile at the house down the street that's ready, and now you're behind that job. The plumber can't set your fixtures until the tile is in, and everything after it slides too. One decision you haven't made holds up a bunch of people, sometimes for weeks.

Start here. Ask your builder for the trade schedule: the order the trades come through your house, with rough dates. The three steps below all hang on it.

Get the trade schedule from your builder. The order the trades come through, with rough dates.
Line up every decision under its trade. Section 02.
Keep every decision in one place. Section 03.
Order by lead time, against the same schedule. Section 04.
02 Line up every decision under its trade

Take the trade schedule and, under each trade, write what it needs from you. Then give every one of those decisions a due date a couple of weeks before its trade shows up. Here's what that looks like for three of them.

Plumber: your faucets, your shower valve, your tub filler, even the niche. The niche is that little shelf built into your shower wall. All of it is decided before his pipes go in the walls, because every plumbing decision affects what's behind them, and changes after that cost much more.
Tile setter: the tile and the layout. Where it starts and where it stops, not just the tile.
Electrician: where you want the outlets. His wires go in before the walls close, so the drywall crew can't start until he's done. He asks while the house is still just studs, so have your answer ready.
Every other trade on your schedule. Ask your builder what each one needs from you, and write it under that trade.
A due date on every decision. A couple of weeks before its trade shows up.
03 One place for every decision

I call it a selections binder, and honestly, a shared folder is fine. What matters is that it's one place, and your builder can open it too.

Every product. What it is, and which room it goes in.
Every finish. Written down where your builder can see it.
Every model number. So nobody has to guess which one you meant.
Every paint color. With the room it goes in.
Shared with your builder. He can find the answer without calling you.

The three-day wait. If your contractor has to stop, ask a question and wait three days for an answer, he has to reschedule a trade. With fewer trades to go around, that pause is how you lose one: he takes another job while he waits.

04 Order by lead time

Lead time is how long something takes to reach you after you order it. Some plumbing fixtures can take months. Custom cabinets can take longer. Even things that say in stock can take weeks to get to you. So ask every vendor one question:

The vendor question
When do you realistically need my order so it doesn't hold up construction?

Then order backwards from the trade schedule: take the date each trade pulls up, step back by that item's lead time, and that's your order-by date. The goal is everything sitting on site before the trade who installs it pulls up.

Now put it all on one sheet, the lineup, and hand it to your builder.

My lineup
Trade: ___ Shows up (rough date): ___
Decisions it needs from me: ___
Decided by (a couple of weeks before): ___
Items to order: ___
Vendor's answer, when they need my order: ___
Order-by date: ___
In my selections binder: yes / not yet

(Repeat for every trade on the schedule, in the order they come through.)

Codes and schedules vary. Check every date and requirement with your builder.

If everything's ready every time a trade pulls up, that's the job they'll want to come back to.

Sources

Nicole's LibraryLibrary card
Free access

Keep reading free with your library card

One email opens this checklist and all 21 resources in Nicole's library. No account, no password.

It opens right here, and a copy goes to your inbox. You'll also get Nicole's new resources. Unsubscribe in one click.

Thanks
You finished it
Now do one thing

Ask your builder for the trade schedule today, then write under the first trade on it the decisions it needs from you.