- 0:00 The slowest part isn’t the framing
- 0:16 What NAHB’s builders reported
- 0:46 What counts as a finish
- 1:08 The fun part is the slow part
- 1:44 Homes built to sell, and yours
- 2:30 The order to pick your finishes
- 3:12 My order: flooring first, paint near the end
- 3:51 When the finishes wait on you
- 4:34 Three ways to stay on schedule
The National Association of Home Builders just timed every stage of building a house, and the slowest part isn’t the framing. It’s the finishes, the part you’ve been saving on Pinterest. And if you’ve ever stood in a half-built house asking, why is this taking so long, this is your answer.
What the builders reported
On November 2, they shared what builders told them in their October survey. That’s a survey they send to builders across the country every month, and this time they asked how long each stage of a new house takes.
- The whole house came out to about 25 weeks.
- Framing, which is basically the whole skeleton of the house, takes a little under four weeks.
- The rough-ins, so the plumbing, wiring and heating inside the walls, take about the same.
- The interior finishes take 6.4 weeks. That’s longer than any other stage.

What counts as a finish
It’s the drywall, the interior doors, the paint, the cabinets, the countertops, the floors, even the sinks and the faucets. So basically the inside of your house, everything you actually touch and look at every day.
And it’s not only the slowest stage. The builders say it’s the most expensive one too, about a quarter of what it costs them to build the house.
The fun part is the slow part
Honestly, that doesn’t surprise me at all. Framing is mostly one crew doing one big job. Finishes are a line of trades, the flooring crew, the cabinet installers, the countertop fitters, and each one waits on the one before it.
The floors go in, then the cabinets. After that, there’s a pause before anyone can measure for the countertops, because they measure the real cabinets, not the drawing. Once the counters are in, the backsplash goes up, and the faucet goes on last.
And during that pause, it can look like nothing is happening. Just because you don’t see progress doesn’t mean progress isn’t happening.
Homes built to sell, and yours
One thing to keep in mind. This survey is about homes builders build to sell, so not homes built one at a time for one family. In a lot of those, the builder has already made most of the choices.
If you’re building a custom home on your own lot, it’s longer. The same builders’ group puts a custom home at about 14 months, from the permit to done. And in your build, the chain has one more thing it can end up waiting on, and that’s you. Which floor, which cabinets, which tile. The crew can’t keep going until you decide.
You can’t make paint dry any faster, but you can make sure nobody on your job site is standing around waiting on you.
The order to pick your finishes
There’s an order, and it’s probably not the one you’d guess. Most people pick the finishes in the wrong order. They start with the paint, and then the floor and cabinets they want don’t go with it, or aren’t ordered yet. That’s how a crew ends up in your kitchen with nothing to install.
I get it. Paint is the fun one. You’ve got 40 swatches taped to a wall in your head. But paint is one of the last things I decide, because it’s one of the easiest things to change. There is an order, and the more closely you follow it, the easier your project becomes.
For me:
- Flooring comes first.
- After that, the cabinetry, the countertops and the tile.
- Then the plumbing fixtures and the hardware.
- Paint near the very end.

Big decisions first, little decisions second.
Here’s why that order matters. Each choice gets made around the one before it. Once your floor is picked, the thousand cabinet colors you’ve saved become maybe ten, because the cabinets have to look right next to that floor.
And I know you’re busy, so let me take some pressure off. The key isn’t making all the decisions faster, it’s knowing which decisions to make first. So decide the big things on paper, in that order, before the first shovel goes in the ground.
I put every finish choice, in the order I’d make them and with the date each one is due, into a free checklist.
When the finishes wait on you
Once your choices are made, there’s one more way to keep the finishes stage, about six weeks, from stretching. One home builder said the biggest cause of delays on custom homes isn’t the weather or the permits or material shortages, it’s the homeowner making their choices late.
That’s one builder, talking to a company that sells software to builders. But from what I’ve seen on job sites, it’s not far off. That’s mostly because later has a funny way of arriving much faster than people think.
I’ll be honest, it happens to me too. Years ago, we really thought we’d move into our own renovation after six months, and it took about a year and a half. When later shows up, everyone is standing around waiting for an answer, and usually, it’s your contractor, waiting on you.
Three ways to stay on schedule
- Ask when they need each decision. Your builder will give you a deadline for your selections, and selections is just the builder’s word for every finish you choose. But that deadline is the day they need it, not the day you should start. So ask them, when do you need my decision on each finish?
- Put a date on every decision. Instead of saying, I’ll think about it, say, I’ll make this decision by Friday.
- Once you’ve ordered the tile, stop looking at tile. Changing one finish is never just one change. Swap the floor, and now the stairs, the baseboards and the cabinet color are all back on the table. One decision turns into seven.
The whole order and all three of these are in the free checklist.
The finishes will always be the longest part of the build. They just don’t have to be the part where everyone waits on you.
So tell me. Have you already picked your flooring, or is it still a Pinterest board?
Questions people ask
What is the slowest part of building a house?
The slowest part isn’t the framing. It’s the finishes. The interior finishes take 6.4 weeks. That’s longer than any other stage.
How long does it take to build a house?
The whole house came out to about 25 weeks. The same builders’ group puts a custom home at about 14 months, from the permit to done.
What counts as a finish in a new house?
It’s the drywall, the interior doors, the paint, the cabinets, the countertops, the floors, even the sinks and the faucets. So basically the inside of your house, everything you actually touch and look at every day.
Why do the finishes take so long?
Finishes are a line of trades, the flooring crew, the cabinet installers, the countertop fitters, and each one waits on the one before it.
In what order should you pick your finishes?
Flooring comes first. After that, the cabinetry, the countertops and the tile. Then the plumbing fixtures and the hardware, and paint near the very end. Big decisions first, little decisions second.
How do you keep the finishes on schedule?
Ask your builder when they need your decision on each finish. Put a date on every decision. And once you’ve ordered the tile, stop looking at tile.
Sources
Your next step
01
This checklist · free
The Finish Order Checklist
Every finish choice in the order I’d make it, a place for the date each one is due, and three ways to keep the finishes from waiting on you.
Your first moveAsk your builder when they need your decision on each finish, then write your own date next to each one.
02
Nicole’s Library · free
Get free access to Nicole’s whole library
One email opens every checklist from Nicole’s videos, right here on the site, and each new one as she adds it.
- Who Gets a Vote Checklist
- Stay-or-Go Checklist
- Teammate Ladder: How to Raise a Problem With Your Builder
- Kitchen Traffic Checklist
- Open Walls Checklist
- Cushion: Your Renovation Budget Template
- Electrical Walkthrough Checklist
- Last Payment Checklist
- Kids’ Room Furniture Checklist
- Lineup: Your Trade-by-Trade Decision Checklist
- New Build Protection Checklist
- Laundry Walk-Through Checklist
- Decide Together Worksheet
- Appliance Specs Checklist
- Lighting Plan Checklist
- Finish Order Checklist
- Before-Drywall Checklist
- Contractor Interview Checklist
- Cabinet Order Checklist
- Countertop Promise Checklist
- Picture-to-Plan Checklist
03
Work with Nicole
Already mid-project?
Through R. Nickson Interiors, my team designs and manages whole-home projects. Or learn the process yourself with The Highly Designed Home Method.