- 0:00 Home building lost 16,400 jobs in October
- 0:18 Most of them were the trades
- 0:44 Half a percent? Look at everything around it
- 1:15 My own house waited on my clients
- 2:01 When nobody’s picked the tile
- 2:41 Be the job that’s ready
- 2:53 The electrician’s one question
- 3:23 Two timelines on every build
- 3:37 Line up every decision under its trade
- 4:09 Keep every decision in one place
- 4:36 Order by lead time
- 5:15 The job they’ll want to come back to
America added 165,000 jobs in October. Home building lost 16,400. That’s the Bureau of Labor Statistics, and it’s the worst month for home building jobs since March of 2021. If you’re planning to build in the next six months or so, those are the people your house is going to need.
Most of them were the trades
Almost all of those jobs, about 15,200 of them, were the specialty companies your builder hires for each part of the job, what the industry calls the trades: your electrician, your plumber, the drywall crew, the tile setter, the painter.

About 3.3 million people work in home building, and around 2.3 million of them work for the trades. So most of the people building your house don’t even work for your builder.
Half a percent? Look at everything around it
You might be thinking, 16,000 out of 3.3 million, that’s half a percent. Why would I care? And honestly, on its own, I wouldn’t. It’s a first estimate, and those numbers do get revised.
What I’d look at is everything around it. In September, construction had 298,000 jobs nobody had filled yet. And more people quit construction jobs in September than a year before. So fewer people, more open seats, and more of them leaving. That means a good trade has options.
My own house waited on my clients
I know what a trade with options does. I’m a designer with a construction background, I run building projects for my clients, and I’m usually the one deciding where the trades go.
When we renovated our own house, I didn’t hire a contractor. I hired each trade myself. I’ve run projects for about 20 years, so I figured, we can do this. But I kept finding myself sending my wallpaper installer to a client’s house, and my tile guys to a client’s house, because I put my clients’ houses first. My family lived in the guest room behind plastic for a while, and they were thrilled about it, as you can imagine.
That’s the thing about getting on someone’s schedule. You can’t always tell when they’ll actually make it to you. Every good trade is making choices like that every week. And the easiest yes is the job that’s ready.
When nobody’s picked the tile
Picture what not ready looks like. Your tile setter shows up on a Monday, ready to go, and nobody’s picked the tile yet. He can stand around, or he can go set tile at the house down the street that’s ready. And once he books that job, you’re behind it, so getting him back can mean waiting for that house to finish first.
Meanwhile, the plumber can’t set your fixtures until the tile is in, and everything after it slides too. So one decision you haven’t made holds up a bunch of people, and sometimes it holds them up for weeks.
I put every decision your trades will need from you, lined up in the order they’ll need it, on one free checklist I call the lineup.
You can’t make more trades show up. But you can be the job that’s ready when they pull up. And it starts with knowing which decision each trade needs from you, and when.
What a ready job looks like
An electrician walks through a new house that’s still just studs and asks the family one question: where do you want the outlets? They don’t know yet. So he books another job across town, and now the drywall crew can’t start until he comes back, because his wires go in before the walls close.
The Bureau of Labor Statistics counted 16,400 fewer home building jobs in October, almost all of them the trades. So when one walks away, that’s how a build loses weeks. It’s also the part you can control.
There are two timelines on every build. There’s the construction timeline, that’s the trades. And there’s the decision timeline, that’s you. The goal is to keep the decision timeline one step ahead of construction, and three things keep it there.

Three things keep you one step ahead
1. Line up every decision under the trade that needs it. Ask your builder for the trade schedule. That’s the order the trades come through your house, with rough dates. Then, under each trade, write what it needs from you. Your plumber needs your faucets, your shower valve, your tub filler, even the niche, that little shelf built into your shower wall, before his pipes go in the walls. Your tile setter needs the tile and the layout, where it starts and where it stops, not just the tile. And give every one of those decisions a due date a couple of weeks before its trade shows up.
2. Keep every decision in one place. I call it a selections binder, and honestly, a shared folder is fine. Every product, every finish, every model number, every paint color, and your builder can open it too. Because if your contractor has to stop, ask a question and wait three days for an answer, he has to reschedule a trade. And with fewer trades to go around, that pause is how you lose a trade. He takes another job while he waits.
3. Order by lead time, against that same schedule. Lead time is how long something takes to reach you after you order it. Some plumbing fixtures can take months. Custom cabinets can take longer. Even things that say in stock can take weeks to get to you. So ask every vendor one question:
When do you realistically need my order so it doesn’t hold up construction?
Then order backwards from the trade schedule, so everything is sitting on site before the trade who installs it pulls up.
The trade schedule, every decision lined up under it, and the order-by dates are all on the lineup checklist, so you can hand it to your builder.
The job they’ll want to come back to
Nobody can hire the trades back for you, not even your builder. But if everything’s ready every time one pulls up, that’s the job they’ll want to come back to.
So, do you have your trade schedule yet?
Questions people ask
Why do the trades matter so much when you build a house?
Most of the people building your house don’t even work for your builder. They are the specialty companies your builder hires for each part of the job: your electrician, your plumber, the drywall crew, the tile setter, the painter.
What happens when a trade shows up and the job isn’t ready?
Your tile setter shows up on a Monday and nobody’s picked the tile yet. He can go set tile at the house down the street that’s ready, and once he books that job, you’re behind it. One decision you haven’t made holds up a bunch of people, and sometimes it holds them up for weeks.
What is a trade schedule?
That’s the order the trades come through your house, with rough dates. Ask your builder for it, then under each trade, write what it needs from you.
When should each decision be due?
Give every one of those decisions a due date a couple of weeks before its trade shows up.
What is lead time?
Lead time is how long something takes to reach you after you order it. Some plumbing fixtures can take months, and custom cabinets can take longer.
What should I ask every vendor before I order?
When do you realistically need my order so it doesn’t hold up construction? Then order backwards from the trade schedule, so everything is sitting on site before the trade who installs it pulls up.
Sources
Your next step
01
This checklist · free
The Lineup: Your Trade-by-Trade Decision Checklist
The trade schedule, every decision lined up under the trade that needs it, one place for all of it, and the order-by dates, on one checklist you can hand to your builder.
Your first moveAsk your builder for the trade schedule today, then write under the first trade on it the decisions it needs from you.
02
Nicole’s Library · free
Get free access to Nicole’s whole library
One email opens every checklist from Nicole’s videos, right here on the site, and each new one as she adds it.
- Who Gets a Vote Checklist
- Stay-or-Go Checklist
- Teammate Ladder: How to Raise a Problem With Your Builder
- Kitchen Traffic Checklist
- Open Walls Checklist
- Cushion: Your Renovation Budget Template
- Electrical Walkthrough Checklist
- Last Payment Checklist
- Kids’ Room Furniture Checklist
- Lineup: Your Trade-by-Trade Decision Checklist
- New Build Protection Checklist
- Laundry Walk-Through Checklist
- Decide Together Worksheet
- Appliance Specs Checklist
- Lighting Plan Checklist
- Finish Order Checklist
- Before-Drywall Checklist
- Contractor Interview Checklist
- Cabinet Order Checklist
- Countertop Promise Checklist
- Picture-to-Plan Checklist
03
Work with Nicole
Already mid-project?
Through R. Nickson Interiors, my team designs and manages whole-home projects. Or learn the process yourself with The Highly Designed Home Method.